European Metals Holdings Ltd PFS shows Cinovec as potential low cost producer

European Metals Holdings Limited (LON:EMH) have today announced the successful completion of the Preliminary Feasibility Study (“PFS”) for development of the Cinovec Lithium and Tin Project, which highlights that Cinovec could be a low cost lithium carbonate producer.

Highlights (all $ figures in this release are US Dollars):

· Net overall cost of production – $3,483 /tonne Li2CO3

· Net Present Value (NPV) – $540 M (post tax, 8%)

· Internal Rate of Return (IRR) – 21 % (post tax)

· Total Capital Cost – $393 M

· Annual production of Battery Grade Lithium Carbonate – 20,800 tonnes

· Study based on only 9.9% of defined Indicated Mineral Resources

The completion of the PFS follows a comprehensive metallurgical test-work campaign managed by European Metals. The PFS has been prepared by the Company based on technical reports undertaken by independent consultants who are specialists in the required areas of work. These included:

· Resource Estimation – Widenbar and Associates Pty Ltd;

· Mining – Bara Consulting Ltd;

· Front-End Comminution and Beneficiation (“FECAB”) – Ausenco Limited; and

· Lithium Carbonate Plant (“LCP”) – Hatch Pty Ltd.

The study is based upon a mine life of 21 years processing on average 1.7 Mtpa of ore, producing 20,800 tpa of battery grade lithium carbonate via a sodium sulphate roast.

European Metals Holdings Ltd Managing Director Keith Coughlan said, “I am very pleased to report the headline numbers for the Cinovec Preliminary Feasibility Study. The study highlights the potential for Cinovec to be the world’s lowest cost hard rock producer of lithium carbonate due to its unique geological and metallurgical characteristics. These results, coupled with the macro outlook for the lithium industry, particularly in Europe, highlight the attractiveness of the project. As a result, we will move directly into a definitive feasibility study to accelerate the project towards development.

Cinovec is strategically located in central Europe in close proximity to the majority of the continent’s vehicle manufacturers. With increasing demand for Electric Vehicles, and Cinovec’s status as the largest and most advanced European lithium project, the project is very well placed to supply the European lithium market for many decades.”

The Cinovec Project is potentially the lowest operating cost, hard rock lithium producer globally, due to a number of unique advantages:

· By-product credits of tin, potash and tungsten;

· The ore is amenable to single-stage crushing and single-stage coarse SAG milling, reducing capital and operating costs, whilst reducing complexity;

· Paramagnetic properties of zinnwaldite allow the use of low cost wet magnetic processing to produce a lithium concentrate for further processing at relatively high recoveries;

· Low temperature roasting and reagent recycling;

· Low cost access to extensive existing infrastructure and grid power;

· Highly skilled workforce and comparatively low costs of employment;

· Historic mining and chemical plant region – strong support by the local community for job creation in areas that have both historic and current operations;

· The deposit lies in a stable jurisdiction, located centrally to the rapidly expanding electric vehicle industry, which is forecast to be the main driver behind increasing lithium consumption; and

· Established and transparent mining code.

(Please refer to the announcement on the European Metals Website for the graphic of Figure 1 – Operating Cost Comparison with Competing Projects – www.europeanmet.com.)

Summary of PFS
The Cinovec Project hosts a JORC 2014-compliant global Resource of 656.5 Mt in the Indicated and Inferred categories as shown in Table 1 below (see announcement dated 20th February 2017).

Table 1: JORC 2014 Cinovec Mineral Resource Estimate (19 February 2017)
JORC Cut-off Tonnes Li Li2O LCE W Sn
CATEGORY % (Millions) % % kt % t % t
INDICATED 0.1 % Li 347.7 0.2 0.5 3,890 0.015 52,160 0.04 139,080
INFERRED 0.1 % Li 308.8 0.2 0.4 2,960 0.014 43,230 0.04 123,520
TOTAL 0.1 % Li 656.5 0.2 0.4 6,990 0.014 91,910 0.04 262,600

Notes:

1. Mineral Resources are not reserves until they have demonstrated economic viability based on a feasibility study or pre-feasibility study.

2. Mineral Resources are reported inclusive of any reserves and are prepared by Widenbar in accordance with the guidelines of the JORC Code (2012).

3. The effective date of the Mineral Resource is February 2017.

4. All figures are rounded to reflect the relative accuracy of the estimate.

5. The operator of the project is Geomet s.r.o., a wholly-owned subsidiary of EMH. Gross and Net Attributable resources are the same. Any apparent inconsistencies are due to rounding errors. LCE is Lithium Carbonate Equivalent and is equivalent to Li2CO3.

6. There has been no change to this Mineral resource statement since publication.

The PFS is based on mining 34.5 Mt of material, 100% of which lies within the Indicated Mineral Resource category. The tonnage used in the PFS represents only 5.2% of the total Mineral Resource and 9.9% of the Indicated Mineral resource.

Around 1.7 million tonnes of ore per annum is mined and crushed in the underground mine prior to being conveyed 1,800 m to the mine portal and stacked on Comminution Plant stockpile (30 kt live capacity), providing a buffer and surge capacity between the underground activities and the processing plants.

The ore is reclaimed from the stockpile to be delivered to the start of the Front-End Comminution and Beneficiation (FECAB) circuit that comprises two sections of plant, geographically separated and connected by a slurry pipeline. The Comminution Plant featuring a single stage 4 MW SAG mill is located near the mining portal and delivers milled ore (P80 < 212 μm) via 7 km slurry pipeline to the Beneficiation Plant, which is located adjacent to the Lithium Carbonate Plant (LCP).

The beneficiation plant uses Wet High Intensity Magnetic Separation (WHIMS) to separate out the lithium bearing micas (zinnwaldite) and produce a magnetic mica concentrate. The ability to use wet magnetic separation is unique to zinnwaldite ore because zinnwaldite contains iron in its lattice and is paramagnetic. Magnetic separation offers cost and recovery advantages over benefaction through froth flotation.

The LCP receives the mica concentrate from the Beneficiation plant and extracts the lithium through roasting, leaching and then purification to produce battery grade lithium carbonate. The plant also produces a potassium sulphate by-product that becomes an additional revenue source. The tailings produced by both processing plants are filtered to produce a filter cake which is dry stacked in a nearby Tailings Storage Facility (TSF). Although higher cost than alternative methods, dry stacking significantly reduces environmental impact.

As confirmed by testwork conducted in both Anzaplan (Germany) and Nagrom (Perth), the quality of the lithium carbonate produced by the LCP will meet requirements for use in lithium battery manufacturing, for which there is a growing market, strong demand and supply shortages. Current market conditions support the lithium carbonate price of $10,000/tonne used in the economic model.

The quality of the anticipated lithium carbonate product has been confirmed by ongoing testwork programs conducted at both Anzaplan GmbH (Germany) and Nagrom Metallurgical (Perth).

Natural gas is delivered to the project fence by pipeline, supplying low cost energy for roasting the mica concentrate and heating the underground mining operations. The electricity requirement of 22 MW can be obtained from the existing local grid by constructing 1,000 m overhead line to the nearby existing switchyard in Teplice.

Potable and industrial water for processing make-up requirements can be purchased from the local municipality, although dewatering will supply the bulk of process water requirements.

(Please refer to the announcement on the European Metals Website for the graphic of Figure 2 – Overview of flowsheet – www.europeanmet.com.)

Cinovec Project Background
The Cinovec Project is located in the Krusne Hore Mountains which straddle the border between the Czech Republic and the Saxony State of Germany. The project is within an historic mining region, with artisanal mining dating back to the 1300s.

In the 1940s a large underground mining operation was established primarily to produce tungsten for the war effort. Mining and processing activities continued under the Czechoslovakian Government with the mine continuing to expand and producing tin as well as tungsten. Due to the fall of communism and lower tin prices, the mine was closed in 1993. In 2011, the old processing plant was removed and the site rehabilitated.

In 2014, European Metals commenced a drilling campaign to validate the comprehensive data generated by the earlier exploration activities. The Company’s on-going drilling programme has completed 26 diamond holes for a total of 9,477m drilled, successfully validating earlier drilling results, adding lithium grade data and providing metallurgical testwork samples

In 2015, European Metals completed a Scoping Study for redevelopment of the Cinovec Project (“2015 Scoping Study”). The 2015 Scoping Study highlighted that the size, grade and location of the deposit make it a very attractive development opportunity and recommended that the project proceed through to a Preliminary Feasibility Study. The flowsheet the 2015 Scoping Study was based on was the as yet un-commercialised L-Max process proprietary to Lepidico Ltd. Using forecast long term metal prices, the 2015 Scoping Study estimated a pre-tax Internal Rate of Return (IRR) of 24% and NPV of $310 M.

A trade-off study was completed in November 2016 comparing the operating and capital costs of the conventional sodium-sulphate roast and the L-Max process. It was concluded that conventional roasting technology would deliver high lithium recoveries with a lower operating cost, lower technical risk, less impurity removal, and be less dependent on potassium by-product credits. The Company has selected the sodium-sulphate roasting option as the preferred method of lithium extraction for the PFS.

Mining
The mine design and scheduling has been completed by Bara Consulting of Johannesburg (“Bara”).

Geotechnical Data Gathering and Rock Characterisation

A site visit was carried out by Bara in October 2016, during which a quality assurance – quality control (QAQC) was undertaken on borehole logging data generated by EM. Bara also undertook geotechnical logging of core on site and selected rock samples for laboratory testing.

The data collected was transformed into rock mass quality by using classifications such as Rock mass rating (RMR89), Geological Strength Index (GSI) and Q-index (Q and Q’). Laboratory testing of core samples included uniaxial compressive strength with elastic moduli (UCM), triaxial compressive strength (TCS), indirect tensile strength (UTB) and base friction angle (direct shear) tests (BFA).

The output information from the geotechnical characterization phase was used to derive the underground mine design criteria. The derived mine design criteria for Cinovec are summarised in the table below:

Table 2: Geotechnical Criteria

CINOVEC MINE DESIGN CRITERIA

Aspect

Description

Value

Spans

Maximum stope spans

13.0m

Potvin’s Stability number

Crown (Rhyolite)

19.70

Hanging wall (Greisen + Granite orebody)

39.40

Footwall (Albite Granite)

52.70

Endwalls (Greisen + Granite orebody)

39.40

Hydraulic radius

Stability graph

Matthews-Potvin,1992

Extended Matthews,2002

Crown (Rhyolite)

7.20

9.2

Hanging wall (Greisen + Granite orebody)

9.30

15

Endwalls (Greisen + Granite orebody)

9.30

15

Critical strike span

Stope height (m)

Stope length (m)

25.0

80

20.0

90

15.0

90

10.0

90

Rib pillar widths [m]

Stope height (m)

 Pillar width(m)

25.0

7.0

20.0

6.0

15.0

5.0

10.0

4.0

Sill pillar widths  [m]

Stope height (m)

Pillar width (m)

>25.0

6.0

<25.0

No sill pillars for stope height less than 25.0m

Crown pillar dimension

Crown pillar width (minimum)

40m

 

Support Strategy

Primary support design guidelines proposed by Barton et al., (1974) which are based on rock mass classification parameters were used for the derivation of systematic support strategy of excavations for Cinovec. The table below presents the derived tendon support spacings and sizes based on Barton’s empirical formulas. Other support units offering areal coverage like wire mesh and shotcrete are to be used in areas where poor ground conditions persist.

Table 3: Support Requirements

TENDON SUPPORT SPECIFICATIONS FOR CINOVEC

Excavation

Jr

Q

ESR

Span (m)

Support pressure (kPa)

Tendon length (m)

Tendon spacing (m)

Calculated

Recommended

Calculated

Recommended

Decline

1.5

1.9

2.0

6.0

108.25

1.45

2.20

1.3

1.0

Footwall drives

1.5

21.8

1.6

5.0

47.78

1.72

2.20

1.9

1.5

Ore drives

1.5

11.2

3.0

5.0

59.64

0.92

1.30

1.7

1.5

Passing bays

1.5

1.9

1.6

5.0

108.25

1.72

2.20

1.3

1.0

Cross cuts

1.5

21.8

1.6

5.0

47.78

1.72

2.20

1.9

1.5

Mining Method

The geometry of the payable ore is largely flat or shallow dipping and massive enough to mechanise using long-hole open stope mining.

An evaluation was completed to establish the achievable extraction ratios with and without backfill, based on the geotechnical design criteria including pillar sizes and stope spans (see above). The preferred option was to mine with pillars support only, negating the requirement for a backfill plant.

The payable ore will be split into blocks approximately 90 m long in the strike direction and 25 m high. The bottom of each block will be accessed in the central position by an access crosscut and the block will be developed from the centre to the strike limit by drifting. The stope will then be mined on retreat from the block limit, retreating to the access cross cut position. The stopes will be a maximum of 13 m wide with rib pillars between stopes of 4 to 7 m wide depending on stope height.

Access to the stopes will be by footwall drives developed in the footwall at 25 m vertical intervals. All stope access crosscuts will be developed out of the footwall drives.

The mine will be accessed by a twin decline system. A conveyor will be installed from the underground primary crusher on 590m Elevation to surface in the conveyor decline. The second decline will be used as a service decline for men, material and as an intake airway.

The modifying factors used to generate the mining inventory used in the study from the Indicated Mineral resource are:

· Un-planned dilution 3%;

· Un-planned ore loss 3%; and

· Exclusion zones, any ore within 70 m vertical distance from surface was excluded from the mine plan. In the northern areas where mining occurs below the village the crown pillar exclusion was increased to 150 m.

Underground Infrastructure

Underground infrastructure designs take into consideration the life of mine plan and aims to support the underground mining production and development activities. Underground infrastructure comprises:

· Mine service water systems;

· Mine dewatering systems, including clear and dirty water pump stations;

· Mine electrical reticulation;

· Control systems and instrumentation;

· Trackless workshops;

· Refueling bays; and

· Underground crushers, tips, and conveyors.

Surface Infrastructure

Surface infrastructure supports the mine plan with consideration of the labour and mechanised equipment requirements of the operation in addition to the movement of rock, men and materials. The infrastructure is divided into two distinct areas, with the area at the portal servicing the initial development requirements and the second servicing the production phase.

(Please refer to the announcement on the European Metals Website for the graphic of Figure 3 – Mine Design and Schedule – www.europeanmet.com.)

(Please refer to the announcement on the European Metals Website for the graphic of Figure 4 – Life of Mine Grade and Tonnages – www.europeanmet.com.)

Table 4: Mining Physicals

PHYSICALS (LOM)
 Life of mine  years                           22
 ROM – ore mined  mt                     34.46
 Tin
 Grade  % 0.09
 Tungsten
 Grade  % 0.03
 Lithium
 Grade (Li2O)  % 0.65

Processing
European Metal’s approach for operation of the project as a whole is to provide a constant feed rate of 360,000 tonnes per year of mica concentrate to the LCP. The Comminution and Beneficiation plants will therefore vary operating hours to accommodate fluctuations in the mine feed grade, to produce the required level of mica production.

(Please refer to the announcement on the European Metals Website for the graphic of Figure 5 – Mining and Processing Throughput – www.europeanmet.com.)

Processing Testwork
Front End Comminution and Beneficiation Testwork

This phase of testwork concerned the beneficiation of primary crushed ROM ore, by primary comminution followed by concentration of zinnwaldite by wet magnetic separation to produce a mica-concentrate, which is further treated by the downstream lithium carbonate plant.

Liberation: Across all lithologies the lithium bearing mica, zinnwaldite, is effectively liberated from the gang material with a top-end particle size of less than 300 µm. Initial liberation analysis was supported by Heavy-Liquid Separation (HLS) of minerals from each of the various lithologies. This was followed by detailed liberation, mineralogical and petrographic analysis using QEMSCAN of SAG milled composites with a P80 passing 212 µm. These results confirmed those from the HLS tests.

Lithium Concentration: Initial studies investigated both froth flotation and magnetic separation for concentration of zinnwaldite. Magnetic separation was proven to be far superior (91% lithium metallurgical recovery versus 78%) and was selected as the method to be optimized for the PFS.

To ascertain the performance of the chosen method and to allow finalization of the circuit, two composites where produced to reflect a high-grade and low-grade lithium ROM feed. A pseudo-lock-cycle flow sheet was implemented to test the effects of variability of grade and the effects of improving lithium recovery via scavenging.

The results showed that an additional Wet High Intensity Magnetic Separation (WHIMS) stage could be used to upgrade the para-magnetic material to produce a scavenger magnetic fraction, which is sent back to the start of the circuit. The testwork has resulted in an estimated lithium recovery of 91% to the concentrate using a 3-stage magnetic separation flow sheet comprising a rougher, cleaner, and scavenger stage. The cleaner magnetic concentrate was reground and passed over a shaking table to recover liberated tin. The gravity concentrate and the scavenger concentrate are returned to the beginning of the circuit.

A lock-cycle gravity testwork program was conducted to simulate the gravity recovery circuit component of the FECAB plant. A pre- concentrate grade of 8 % Sn was produced with an Sn recovery of 80-90% to the magnetic fraction. A dressing circuit was approximated for the testwork by using a Mozley Super-Paner centrifugal separator.

SAGability testwork was conducted at ALS on the three primary lithologies. Cinovec’s ore was determined to be amenable to single stage SAG milling, which forms part of the FECAB comminution design. Wardle Armstrong conducted a Starkey SAGability test along with standard bond ball and bond rod work indexes.

Lithium Carbonate Plant Testwork

Testwork has been conducted at both Anzaplan, Germany and Nagrom, Western Australia.

Initial sodium sulphate testwork conducted at Anzaplan concluded that the optimal mass ratio of mica: sodium sulphate: lime is 6:3:1. This roast resulted in a leach lithium recovery of 82.8% – 87.0% lithium at a roast temperature of 850 °C for 1 hour.

Additional roast optimization testwork then focused on optimising:

· Sodium sulphate ratio;

· Lime ratio;

· Particle size distribution of feed; and

· Roasting residence time.

Based on the best lithium extraction achieved in the roast optimisation testwork, a bulk composite of mica concentrate, produced from representative Cinovec core samples, was roasted at Nagrom, and an initial lithium carbonate produced which had a purity of >99.5%.

To achieve the high purity Lithium Carbonate bicarbonation step was required.

Ongoing testwork is focused on fluoride and silica removal. Initial lime tests have indicated that silica can be removed as well as part of the fluoride content. Initial tests to remove the fluoride down to acceptable levels is encouraging and EMH is confident this can be successfully removed. The acceptable level of fluoride in battery grade lithium carbonate needs to be confirmed with potential offtakers.

Tailings Testwork

Rheology and geochemical work was conducted on various tailings streams. The tests concluded:

· Samples had a definite, but very low level of radioactivity. No U and Th were detected in the SPLP leach; and

· Samples were devoid of sulphides and have no potential to generate acid-mine drainage as confirmed through both the ABA and NAG test. However, the Neutralisation Potential of samples were also very low and samples also had a very low total C content.

No tailings testwork has yet been conducted on the lithium carbonate tailings streams however, the TSF has been designed to incorporate a worst-case scenario and to capture any residual leachate and return it to the plant for processing.

Based on detailed analysis of the testwork results, specific recovery algorithms were developed and entered directly into each block in the block model used for mine scheduling. The average metallurgical recoveries used in the project financial model are summarised below:

· Lithium recovery to concentrate – 90%;

· Lithium recovery in carbonate plant – 85%;

· Overall lithium recovery – 76.5%; and

· Tin recovery – 65%.

Front End Comminution and Beneficiation

Comminution Plant

The purpose of the Comminution Plant (Figure 6) is to reduce the size of the ROM Ore to a particle size Distribution (PSD) that optimises lithium recovery, whilst allowing efficient pumping to the Beneficiation Plant.

Primary crushed Ore is delivered to Coarse Ore stockpile. The Ore is milled to 250 µm in a single stage SAG mill.

The Comminution Plant is run water neutral to remove the need for make-up water or disposal at the mine-site location. This is achieved by returning water from the Beneficiation Plant via a pipeline. Thus, the comminution plant has the advantage of operating at zero water discharge.

(Please refer to the announcement on the European Metals Website for the graphic of Figure 6 – Comminution Plant Layout – www.europeanmet.com.)

The layout of The Comminution Plant maximises the use of the flat land available upon the top of the ridge, shortening the overall footprint. Room has been allowed for future pebble crushing in the SAG mill recirculating load, to allow for retrofitting if conditions warrant.

Beneficiation Plant

The Beneficiation Plant has two functions:

(i) First, to magnetically separate the paramagnetic zinnwaldite to produce a lithium rich magnetic stream (mica-concentrate) to feed the downstream lithium carbonate plant; and

(ii) Second, to then treat the non-magnetics stream with gravity, flotation, magnetic and electrostatic separation to produce tin and tungsten product. Filtered tailings are produced for storage in the TSF.

Magnetic Circuit: Milled product from the Comminution Plant received via the overland pipeline is stored in the Magnetic Circuit Feed Tank. The tank is agitated and acts as a buffer between the Beneficiation Plant and the overland pipeline. The pipeline slurry density is 56% to 58% solids, whilst the discharge density required by the Low Intensity Magnetic Separation (‘LIMS’) is 40% solids. The LIMS magnets reject ferromagnetic species from the slurry prior to the multi-stage Wet High Intensity Magnetic Separation (WHIMS) process.

The WHIMS circuit features a rougher, cleaner, scavenger arrangement. The scavenger retrieves the non-magnetic material from the rougher and cleaner units, and returns the ‘scavenged’ magnetic fraction back to the start of the circuit.

The cleaner magnetic fraction is reground enclose circuit with a spiral to remove reduce the PSD to required LCP feed size. Any tin which is liberated in the process is recovered from the mica-concentrate by the spirals.

(Please refer to the announcement on the European Metals Website for the graphic of Figure 7 – Beneficiation Plant Layout – www.europeanmet.com.)

Non-Magnetics Gravity Circuit: The Non-Magnetics Gravity Circuit treats the Magnetic Separation Circuit’s non-magnetics and concentrates the tin and tungsten minerals for feeding to the Tin Dressing Circuit, where the final product streams are produced. The circuit also has the ability to receive tin and tungsten gravity concentrate as slurry from the Lithium Carbonate Plant.

The circuit incorporates three stages of classification with:

· The coarse fraction is treated by two stages of spirals and two stages of wet tables and also incorporates a regrind mill which is used to achieve the liberation size of the tin and tungsten minerals;

· The medium fraction is treated by two stages of spirals and two stages of wet tables;

· The finer fraction is treated with a flotation and high gravity concentrator; and

· The finest fraction, slimes, is rejected to final tails.

The concentrate produced from the gravity circuit is sent for dressing whilst the tails are dewatered via a thickener and filter.

The dressing circuit upgrades the concentrates through sulphide flotation. Electrostatic precipitation is then used to separate wolframite and cassiterite from the scheelite. Dry magnetics separate the wolframite from the cassiterite to give the final saleable concentrates.

Lithium Carbonate Plant

The current flowsheet is shown in Figure 8. The Lithium Carbonate Plant receives a mica concentrate slurry from the FECAB plant, which is dewatered and stored in covered stockpiles to create a buffer between the FECAB and the LCP. The concentrate is mixed with sodium sulphate and lime before roasting to convert the lithium into a lithium potassium sulphate which dissolves in the leach as lithium sulphate.

The leached slurry is filtered to separate the PLS (pregnant leach solution) from the residue. The leach solution undergoes impurity removal steps to remove calcium, magnesium, fluoride and silica by precipitation and adsorption. Sodium sulphate is then recovered from the leach solution (as Glauber’s Salt) by cooling. The Glauber’s salt is melted and then crystallised as anhydrous sodium sulphate for recycle back to the roaster feed.

Crude lithium carbonate is then precipitated from the PLS by further evaporation and addition of sodium carbonate. The crude lithium carbonate is re-dissolved to form bi-carbonate. The lithium bicarbonate solution is filtered and purified by ion exchange before pure lithium carbonate is re-crystallised by heating the solution causing the bicarbonate to decompose. The battery grade lithium carbonate is then dried, micronised and packaged for sale.

A fertiliser grade potash (potassium sulphate) by-product is also recovered from the depleted lithium carbonate solution (spent liquor). In this circuit, Glaserite double salt (Na3K(SO4)2 sulphate) is precipitated by evaporative crystallisation. Potassium sulphate is then recovered by decomposing Glaserite in water to form soluble sodium sulphate and solid potassium sulphate. The potassium sulphate product is then dewatered, dried and packaged for sale.

(Please refer to the announcement on the European Metals Website for the graphic of Figure 8 – LCP Process Flowsheet – www.europeanmet.com.)

Tailings

All the processing tailings produced by the Beneficiation and Lithium Carbonate Plants pressed into filter cakes to allow dry stack impoundment a close distance from the processing plants. Tailings consists of approximately 1.5 Mtpa of FECAB material and 500 ktpa of LCP material (mostly leach residue).

Although dry stacking is the more expensive compared to traditional wet deposition, it was chosen due to the following advantages:

· The higher safety factors associated with the design versus conventional storage facilities. The region has historic high levels of rainfall thus dry stacking reduces the amount of water to treat by reducing the TSF footprint;

· Progressive rehabilitation is possible, spreading the cost of closure over a longer time when compared to conventional storage facilities; and

· Filtered tailings allow better recovery of lithium by recovering more liquor.

During operations tailings, a dried on a filtered press and dumped on a pad. Wheel loaders and articulated trucks transport the tailings approximately 600 m to the TSF for compaction and impoundment.

An initial TSF cell was designed to accommodate the first two years of combined tailings, with the associated capital cost included in the capital estimate. The TSF is lined and features water collection and diesel powered decant pumps for returning any run off water to the processing plant. 3D model was created to facility the capital cost estimate.

A contractor will be engaged for tailings disposal, an operating cost of $1.50/tonne for LCP tails and $1.0/tonne for FECAB tails is incorporated in the operating cost model.

Environmental
The Project is governed by Act No.100/2001 Coll., on Environment Impact Assessment (hereinafter referred to as the “EIA Act”). The competent authority is the Ministry of the Environment (Environment Impact Assessment Department). An integrated permit is issued upon completion of the EIA process.

The EIA documentation is required to be structured as follows:

· details concerning the notifier;

· details concerning the development project;

· details concerning the status of the environment in the region concerned;

· comprehensive characteristics and assessment of the project impacts on public health and the environment;

· a comparison of project versions (if any);

· a conclusion; and

· a commonly understood summary and annexes (opinion of the Building Authority, opinion of the Nature Protection Authority, expert studies and assessments).

The following expert studies and assessments must be compiled during the EIA Documentation preparation stage:

· noise impact study;

· air quality impact study;

· biological survey;

· human health impact study;

· transport impact study;

· landscape impact study; and

· water quality and hydrology impact study.

In this case, with respect to the location of the project at the border with Germany, an “international assessment” provision applies (Section 13, Act No. 100).

The Company commenced the EIA process with a baseline study, prepared by GET s.r.o an independent Czech based environmental consultancy, which identified the environmental areas to be assessed and determined preliminary outcomes. The underground mine and surface portal is located on the border of or immediately adjacent to environmentally sensitive area. From that perspective, the EIA will focus particularly on project impacts on European protected areas Natura 2000 (protected birds) and mine water discharge into surface streams. The Company has re-positioned key infrastructure to minimise impacts to both the environment and the community and has placed crushing facilities underground to minimise noise as well as enclosing the mill to further reduce noise and visual impacts. Considering the long-term mining history in region and at the deposit itself, the project will not significantly impact the environment.

Operating Cost
The average operating cost for the Cinovec Project is $3,483 per tonne of lithium carbonate, after by-product credits.

Table 5: Average Project Operating Cost

Average Operating Cost (yr. 3-20)

$M pa

$t / ROM

$t / LCE

% Op Cost

Mining

40.7

24.3

1,960

38%

FECAB

19.4

11.6

935

18%

LCP

47.3

28.2

2,274

44%

Overall Project Admin

0.9

0.5

42

1%

Total Operating Cost

108.3

64.6

5,211

By-product Revenue Credits

$M pa

$t / ROM

$t / LCE

Sn/W (yr3-2 0)

29.2

17.4

1,404

Potash

6.7

4.0

324

Excluding Sn/W Royalties & Transportation Cost

Total Opex (Net of By-product Credits)

72.4

43.2

3,483

 

Overhead corporate office costs are excluded. The maintenance costs used in the operating cost modelling includes requirements for sustaining capex. The cost of tailings impounded is included in the above numbers.

An estimated 58% of the project’s operating cost is variable (i.e. changes with the production rate). This high variable percentage improves economic robustness, by giving the operating team the flexibility to easily scale down operating costs if market conditions dictate.

Capital Cost

The estimated capital cost of the Cinovec Project is $393 M based on Q1 CY2017 pricing. The accuracy of the estimate is considered +/-25%. The estimate breakdown is summarised in Table 6 below.

The capital includes all costs for design and construction of the plant and infrastructure on the site for the mine, FECB and LCP, Allowances are also made for connection to off-site services such as gas, electricity and water, construction of a tailings storage facility, project contingency and owners costs including project management team, project approvals, establishment of the operating team and commissioning.

The capital estimate is based on detailed engineering designs produced by the independent consultants and inputs from EMH. Each consultant provided a capital estimate for their respective scope of works. Based on process modelling and mass flow calculations, detailed mechanical equipment lists were compiled, with quotes for all items costing over $100 k. The mechanical equipment list was then used as a base for factoring other project commodities. Material take-offs from the 3D modelling were then used as an integrity check.

As the Project lies on the border of Germany and the Czech Republic it is exceptionally well serviced by supporting infrastructure including access to rail, national highways, power, water, gas, skilled workforce, engineering companies and chemical companies.

 Table 6: Overall Project Development Capital

TOTAL

US$ M

Underground Mining Development

Mining Directs

67.3

Mining In directs

3.0

Total Mining Cost

70.3

Front End Comminution & Beneficiation Plant (FECAB)

Comminution – Direct

25.2

Beneficiation – Direct

40.5

Infrastructure -Direct

20.8

FECAB In directs

18.4

Total FECAB

104.9

Lithium Carbonate Plant (LCP)

LCP Directs

141.9

LCP In directs

38.0

Total LCP Capital

179.9

Total Tailings

2.6

   Overall Project Contingency @10%

35.8

TOTAL CAPITAL COST

393.4

 

In addition, a total of $40m is required in working capital.

Financial Summary
The Cinovec Project yields a post-tax NPV (discounted at 8%) of $540 M and a post-tax Internal Rate of Return of 21%. When operating in steady state the Project achieves an operating cash margin of 59% and has an operating cost of $3,483 per tonne LCE. The key findings of the PFS are set out in Table 7: below:

Table 7: Key PFS Findings

Metric

Value

Metric

Value

NPV @8% Discount

$540 M

Project Breakeven (IRR=0% ) $/t Li2C03

$5,200 /t

NPV @ 10% Discount

$392 M

Avg Li2CO3 Production (yr. 3-20)

20,800 tpa

IRR (Pre-tax)

21.6 %

Avg Potash Production (yr. 3-20)

12,954 tpa

IRR (Post Tax)

20.9 %

Avg Production Cost (without credits)

$ 5,211 /t

Capital Expenditure

 $393 M

Avg Production Cost (with credits)

 $3,483/t

Total Mined Ore

34.4 Mt

Life of Mine

 21 Years

Peak Mill Feed

1.8 Mtpa

Avg Mill Rate (yr. 3-20)

 1.68 Mtpa

Metal Pricing

Metal pricing used for the PFS was as follows:

·     Lithium carbonate –

$10,000/t;

·     Tin –              

$22,500/t;

·     Tungsten –

$330/MTU; and

·     Sulphate of potash –

$520/t.

Lithium is the key driver of the Project. According to Deutsche Bank, global lithium demand increased 15% year on year to 212 kt LCE in 2016, slightly ahead of estimates. Deutsche Bank forecast lithium pricing to remain elevated relative to historical averages, but retrace 15% over 2016 pricing levels. Further, the medium-term outlook is improving and Deutsche Bank has recently lifted their 2019 demand forecast to 380 kt.

The ramp up of new EV model sales from major auto companies is generally considered to be the key driver of lithium demand in the short to medium term. Other factors include the increased production from battery manufacturing facilities and the continued inventory build within the supply chain.

The Cinovec Project is located centrally and within close proximity to a number of major European car manufacturers.

(Please refer to the announcement on the European Metals Website for the graphic of Figure 9 – Lithium End Use – www.europeanmet.com.)

Benchmark expects the average forecasted price range for lithium carbonate 99.95% to be $ 9,500 to $ 13,000/tonne (USD) between 2017 and 2020.

European Metals has considered this forecast in light of other independent forecasts such as Deutsche Bank, and on generally available lithium market commentary.

For the purposes of the PFS with regards to financial modelling, a long-term average price of $ 10,000/t lithium carbonate FOB has been used.

Tax

Tax is calculated at 19% and a 10-year tax free window has been applied as provided for by Czech investment legislation for projects of this scope.

(Please refer to the announcement on the European Metals Website for the graphic of Figure 10 – LOM Cashflow Projections – www.europeanmet.com.)

Key sensitivities of capital cost, key operating costs and revenue are shown in the Figure 11 below.

(Please refer to the announcement on the European Metals Website for the graphic of Figure 11 – Sensitivity Graph – www.europeanmet.com.)

Cost Comparative
The PFS highlights the advantages of the extraction of lithium from Cinovec Ore when compared with spodumene hosted hard rock deposits. The comparison shown in Table 7 assumes a conversion price of $365/t for a Chinese based conversion plant and compares costs for a captured mine, in this case using Pilbara Minerals Limited (ASX:PLS) published DFS numbers, current spot prices (latest Galaxy Resources Limited (ASX:GSY) quoted prices for 6% concentrate) and long term prices as defined in the Pilbara Minerals DFS.

Click to view all articles for the EPIC:
Or click to view the full company profile:
    Facebook
    Twitter
    LinkedIn
    European Metals Holdings Ltd

    More articles like this

    European Metals Holdings Ltd

    Lithium-ion batteries rising as new pillar of Korea’s exports

    Amid concerns about an anticipated slowdown in South Korea’s semiconductor exports this year, lithium-ion batteries for electric vehicles are emerging as a new pillar that will prop up the export-driven economy, said industry officials Monday. According

    European Metals Holdings Ltd

    Lithium-ion battery usage on the rise

    The demand for lithium-ion batteries continues to increase, driven by the growth in hybrid and electric vehicle (xEV) production and the use of lithium-ion batteries in energy storage systems (ESS), according to a report by metals,

    European Metals Holdings Ltd

    Premier Inn unveils UK’s first battery powered hotel

    The UK’s first battery-powered hotel is now operational in Scotland. The Gyle Premier Inn in Edinburgh is trialling a new 100kW lithium-ion battery supplied and installed by E.ON at its 200-room site in a bid to

    European Metals Holdings Ltd

    Electric vehicle manufacturing in China drives metal demand

    As the world’s largest country by population and second-largest economy, China is embarking on a dedicated effort to become a leader in the emerging electric vehicle market. Hundreds of manufacturing firms in China seek to take

    European Metals Holdings Ltd

    Big on batteries: government finally seizes on lithium-ion potential

    The federal government wants to seize a “once-in-a-generation opportunity” to position Australia as a world leader in the rapidly developing lithium-ion battery manufacturing sector. Releasing a new strategy document from Austrade on Tuesday, the investment minister,

    European Metals Holdings Ltd

    What really powers your smartphone and electric car

    The rechargeable lithium-ion battery helps define our era. It powers our smartphones and electric cars, and promises a future where we’re better able to store renewable energy. It also requires lithium and cobalt, minerals that some of the

    European Metals Holdings Ltd

    Companies line up plans for lithium-ion batteries production

    Over a dozen companies ranging from auto component manufacturers to power and energy solutions providers including ExideNSE -0.97 %, Exicom, Amaron, Greenfuel Energy Solutions, Trontek, Coslight India, Napino Auto & Electronics, Amara Raja BatteriesNSE -0.84 %,

    European Metals Holdings Ltd

    China: EVs to boost lithium-ion battery market

    It is anticipated that the Chinese lithium-ion battery market size will increase at a positive double digit CAGR during the period 2017-2022. The demand for lithium-ion batteries in China is expected to grow at a rapid