Caledonia Mining Corporation Plc Extension of Central Shaft Project

Caledonia Mining Corporation Plc (LON:CMCL) following the announcement of an updated resource statement on November 2, 2017 announced today that it plans to extend the depth of the Central Shaft at its 49% subsidiary, the Blanket Mine in Zimbabwe (“Blanket”).

Highlights

· The Central Shaft (which is currently under construction) will be extended by a further 250 metres to a shaft bottom depth of 1,330 metres and fully commissioned by the end of the first quarter of 2020.

· The extension of the Central Shaft will add two further production levels on 34 (1,110 metres) and 38 (1,230 metres) levels, in addition to the two levels that are already planned on 26 (870 metres) and 30 (990 metres) levels.

· The extension and associated capital development of additional production levels will cost approximately $18 million which will be funded by Blanket’s internal cash generation. The additional capital investment is not expected to have any effect on the continuation of Caledonia’s existing dividend.

· A Preliminary Economic Assessment (“PEA”) indicates a project NPV over the Life of Mine of $193 million based on a gold price of $1,260/ounce and a 10% discount rate.

· The addition of two further production levels will provide access to the Indicated & Inferred resources below 30 level and potentially increase Blanket’s projected life of mine by a further four years to 2031.

· The Indicated Resource below 30 level of 37,000 ounces, as a standalone project, justifies the investment of $18 m for the shaft deepening and the additional two production levels.

· Total production from Measured and Indicated resources over the life of the mine is expected to be approximately 420,000 ounces and production from Inferred resources is expected to be approximately 550,000 to 600,000 ounces between 2018 and 2031. Caledonia expects that its long term All-In Sustaining Cost (“AISC”) guidance is expected to remain in the range of $700 to $800 per ounce.

· The extension of the Central Shaft before it has been completed, equipped and commissioned is understood to be significantly cheaper, quicker and less disruptive than a subsequent extension after commissioning.

· Caledonia has also initiated a mid-shaft loading system at Blanket using the existing Central Shaft infrastructure to handle development waste. This is expected to improve Blanket’s waste handling capacity and alleviate pressure on Number 4 shaft which should have a positive effect on both production flexibility and horizontal development.

Commenting on the project update, Caledonia Mining Corporation Plc CEO Mr Steve Curtis said: “We are very pleased that the long track record of sustained resource growth at Blanket, particularly the continued discovery of resources at depth with good grade continuity, supports an extension of the Central Shaft project at Blanket. The Central Shaft is already a transformational project for our business, and to extend the project an additional 250 metres in depth including development on 34 and 38 levels will potentially secure Blanket’s operating future for the next 20 years taking exploration potential into account.”

“Based on the strong geological indications of resource and grade continuity at depth, which was supported by our recent resource update, the excellent progress in the current shaft sinking, and most importantly the strong cash generation from Blanket’s current operations, we are now in a position to continue investing for the future.”

“It is significantly cheaper to continue the shaft sinking while we are in the construction phase of the project rather than to deepen a fully commissioned and operational shaft in several years’ time. The creation of an additional two levels will also increase the mining flexibility and further de-risk the target production of 80,000 ounces per annum from 2021. This leaves Caledonia with a distinct window of opportunity to continue with its investment and I am grateful to both our local partners at Blanket and to the board of Caledonia for their continued support in managing the business for optimal long term value.”

“The adoption of mid-shaft loading at Central Shaft will also make a contribution to reducing the logistical constraints we have experienced so far in 2017; by using the Central Shaft to haul development waste while continuing the sinking process we will be in a position to relieve the pressure on Number 4 Shaft and the associated haulages at 22 (750 metres) level to free up capacity to haul ore. The mid-shaft loading infrastructure should also allow the capital development on the 26 and 30 levels to commence up to ten months earlier than originally planned. Mid -shaft loading is not expected to have any negative effect on the plan to achieve 80,000 ounces of gold production by 2021 or to have any adverse impact on medium term production due to the increased operating flexibility the mid-shaft loading is expected to provide.”

Note: This announcement includes inside information as defined in Article 7 of the Market Abuse Regulation No. 596/2014 and is disclosed in accordance with the Company’s obligations under Article 17 of those Regulations.

Background

The Central Shaft has been under construction since the first quarter of 2015 and was scheduled to be in production during the fourth quarter of 2018. The shaft is currently at a depth of 950 metres below surface and is well advanced towards the previous design depth of 1,080 metres below surface. The shaft was previously expected to support Blanket’s Mine life until 2027 by adding an extra two production levels (26 and 30 levels).

Increased Resource

On November 2, 2017 Caledonia announced an increase in Measured and Indicated resources at Blanket from 671,000 ounces at a grade of 4.23g/t at December 31, 2016 to 714,000 ounces at a grade of 3.95g/t, a 6% increase in contained gold. In addition, Inferred Resources increased by 47% from 604,000 ounces at a grade of 4.99g/t at December 31, 2016 to 887,000 ounces at a grade of 4.99g/t at August 31 2017.

Extension of the Central Shaft

In light of the increased resource base, the boards of Blanket and Caledonia have approved a decision to invest further in the deepening of the Central Shaft to a depth of 1,330 metres to be fully commissioned and operational by the end of the first quarter 2020.

The extension of the Central Shaft is expected to cost approximately $10 million and additional development of the two production levels below 30 level (990m) is expected to cost approximately $8 million. Total incremental project capital expenditure is therefore expected to be an increase of $18 million. The capital cost of deepening the shaft before it is commissioned is expected to be significantly lower and less disruptive than would be the case if the shaft is extended after it’s commissioning by eliminating the duplication of infrastructure at the bottom of the shaft and site re-establishment of shaft sinking equipment and sinking crew.

The deepening of the Central Shaft is not expected to adversely affect the production target of 80,000 ounces of production by 2021 and is expected to extend the life of Blanket by potentially an additional four years beyond the current mine life, based on the existing Indicated and Inferred resources below 30 level to support operations at Blanket until 2031. It is also expected to enable significantly increased operational flexibility at the mine as the deeper shaft will support operations over four production levels rather than the previously planned two levels. This is expected to enable production to continue at the rate of 80,000 ounces until at least 2029 based on the current Inferred Resources below 30 level and potentially longer depending on future exploration success at depth extensions of known ore bodies above 30 level which will also enable exploration below 38 level (1230m).

Mid-Shaft Loading

Blanket implemented a mid-shaft loading system at the beginning of November 2017 to enable Central Shaft to handle development waste, thereby alleviating some of the logistical pressure on Number 4 Shaft and ensuring that the horizontal development on 26 and 30 levels can start at least ten months earlier than the original project schedule. The implementation of mid-shaft loading is also intended to allow Number 6 Winze to hoist ore rather than ore and waste and should reduce waste haulage and hoisting via Number 4 Shaft due to the use of Central Shaft for the hoisting of development waste.

Capital expenditure

The total project capital investment involved in completing the Central Shaft and developing four production levels below 22 level (750m) is estimated to be approximately $51 million over the period 2018 to 2022 which includes $18 million of incremental capital to sink the Central Shaft to the greater depth and develop two additional production levels. Sustaining capital over the anticipated extended mine life is expected to be approximately $63 million over the period 2018 to 2031 (approximately $4 million to $5 million per year) and an additional $11 million of deep level exploration drilling is budgeted for exploration below 22 level. Total life of mine capital investment from 2018 to 2031 (including the extension) for Blanket is expected to be approximately $125 million.

Production Estimates

Total production from Measured and Indicated resources over the life of the mine is expected to be approximately 420,000 ounces and production from Inferred resources is expected to be approximately 550,000 to 600,000 ounces between 2018 and 2031. Caledonia expects that its long term AISC guidance is expected to remain in the range of $700 to $800 per ounce. Given the existing resource classification of Indicated and Inferred resources down to 38 level, a PEA has been prepared in respect of the Inferred Resources which is preliminary in nature and includes Inferred Resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be classified as mineral reserves. There is no certainty that the PEA will be realised.

The changes to the Central Shaft project as stated above result in a revised life of mine plan for the Blanket Mine (the “LOMP”) in terms of which it is anticipated that the approximate production from existing Proven and Probable mineral reserves above 34 level will be as set out below:

Approximate Production from Proven & Probable Mineral Reserves (2018 – 2024)

2018

2019

2020

2021

2022

2023

2024

Tonnes milled (000’s)

564

570

640

720

673

430

133

Gold Production (koz)

59

61

68

80

80

56

19

 

The deepening of the Central Shaft is expected to provide access to the current Inferred Resources down to 38 level and allow for further exploration, development and mining in these sections along the known Blanket strike, which is approximately three kilometers in length. The PEA has been prepared in respect of the Inferred Resources down to 38 level. Based on the PEA, approximate additional production from current Inferred Resources (excluding the projected production set out above) may be achieved in the following indicative ranges:

Approximate Production from Inferred Mineral Resources (2023 – 2031)

2023

2024

2025

2026

2027

2028

2029

2030

2031

Tonnes milled (000’s)

215

494

573

544

594

596

614

425

400

Gold Production (koz)

20 – 24

57 – 62

76 – 80

76 – 80

76 – 80

76 – 80

76 – 80

56 – 60

52 – 56

 

Diamond drilling and development is planned to be continued with the objective of increasing confidence in order to upgrade the categorisation of the resources. The LOMP and the PEA have been reviewed by Mr. Dana Roets, Chief Operating Officer, and Mr. Paul Matthews, Caledonia’s Qualified persons for National Instrument 43-101 Standards of Disclosure for Mineral Projects reporting purposes. A technical report prepared in compliance with National Instrument 43-101 which summarises the revised LOMP and the PEA will be filed on SEDAR before December 17, 2017. The LOMP, Pre-Feasibility Study (“PFS”), PEA, Resource estimation and Reserve conversion have been reviewed by independent consulting firm Minxcon (Pty) Ltd. Minxcon also assisted the Qualified Persons with the compilation of the technical reports. The most important assumptions on which the PEA is based include: a gold price of US$1,260 per ounce; achievement of the targeted production set out above and the accuracy of the projected capital costs.

Funding

Assuming a gold price of US$1,260 per ounce and that all the production projections set out above are achieved, it is expected that all capital expenditure and increased working capital requirements will be funded from Blanket’s internal cash flows and its existing unused credit facilities. It is expected that Caledonia’s net cash resources of $10.8 million as at June 30, 2017 will not be required to fund the project.

Click to view all articles for the EPIC:
Or click to view the full company profile:
Facebook
Twitter
LinkedIn
CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

More articles like this

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Precious metals rally as U.S. dollar extends losses

Gold prices climbed more than 1% to their highest levels in a week on Tuesday and other precious metals also rallied on the back of a sliding dollar, as markets remained focused on the Federal Reserve’s

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Solar power at Caledonia’s Blanket Mine in Zimbabwe

Unstable and unreliable power supply behind the decision to construction the 12.2MW solar power plant at Caledonia’s Blanket Mine Caledonia Mining Corporation, the Jersey-headquartered gold producer, has said that a new solar plant at its Blanket

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Gold prices inch higher

Gold prices edged up on Monday and hovered near the key $1,800-level, as a softer U.S. dollar made the greenback-priced bullion cheaper for buyers holding other currencies. Spot gold XAU= rose 0.1% to $1,800.02 per ounce as of

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Caledonia in the community

Caledonia Mining Corporation plc (LON:CMCL) is a profitable cash generative gold producer with a strong growth profile, Caledonia’s primary asset is the Blanket Mine in Zimbabwe.

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Q3 2022 results presentation

Caledonia Mining Corporation plc (LON:CMCL) is a profitable cash generative gold producer with a strong growth profile, Caledonia’s primary asset is the Blanket Mine in Zimbabwe.

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Caledonia Mining releases new corporate video

Caledonia Mining Corporation Plc (LON:CMCL) has announced that a new corporate video is available on the Company website. Additionally, a video covering Caledonia’s Corporate Social Responsibility initiatives and work within the community is also now available.

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Caledonia Mining launches massive solar power plant

Victoria Falls stock exchange listed gold producer, Caledonia Mining corporation, has erected a solar power plant at Blanket Mine which began generating power yesterday, to hedge itself from electricity challenges that are gripping the country. The

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Caledonia Mining gross revenues up 21% to $107.9 million

Caledonia Mining Corporation Plc (LON:CMCL) has announced its operating and financial results for the quarter and the nine months ended September 30, 2022 (the “Quarter” and “Nine Months” respectively).  Further information on the financial and operating results for the

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Caledonia buys Motapa mining company

Victoria Falls Stock Exchange-listed Caledonia Mining Corporation has bought Motapa Mining Company UK, whose gold claims sit next to Bilboes in southern Zimbabwe. Caledonia has already agreed a deal to buy Bilboes which made Motapa claims

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Caledonia Mining acquires Motapa gold exploration project

Caledonia Mining Corporation Plc (LON:CMCL) has announced that it has purchased Motapa Mining Company UK Limited, the parent company of a Zimbabwe subsidiary which holds a registered mining lease over the Motapa gold exploration property in Southern

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Caledonia Mining says quarterly gold production up 11%

Caledonia Mining Corporation Plc has seen quarterly gold output rising by 11% on the back of records showing the top miner’s sustained productivity output. For the third quarter period ended September 30, 2022, gold output production

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Gold recovers on technical buying

Gold prices rose on Monday, supported by technical trading after the previous session’s steep fall and a pause in the dollar rally, although an impending oversized rate hike by the U.S. Federal Reserve limited bullion’s appeal.

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Caledonia strikes an 11% increase in gold production

Caledonia Mining has announced its gold production from the Blanket Mine in Zimbabwe for the quarter ended September 30, 2022. Gold production hit a high record of 21,120 ounces, superseding a record for any quarter. The

CALEDONIA MINING CORPORATION PLC COM SHS NPV (DI)

Caledonia Mining set a new production record at Blanket

Caledonia Mining Corporation Plc (LON:CMCL) has announced gold production from the Blanket Mine in Zimbabwe (“Blanket”) for the quarter ended September 30, 2022.  All production numbers are expressed on a 100 per cent basis and are based