Bushveld Minerals Limited Lemur Q2 Operational Update

Fortune Mojapelo, CEO of Bushveld Minerals Limited, commented:

“Notwithstanding Bushveld Minerals’ focus on its flagship vanadium platform, the Company is committed to deliver on the value of the Imaloto Power Project by completing the milestones that were set out for this year in order to supply affordable, high quality baseload energy in southwest Madagascar. The granting of the Concession Agreement during the quarter is a critical milestone for the project, aligning its development with the national government’s broader plans.

“We are also pleased that the draft of the bankable feasibility study was submitted by our technical partner, Sinohydro and is currently under review. Once finalised, the study will provide a more precise picture of the project’s cost and timeline for our ongoing discussion with lenders.”

Bushveld Minerals Limited (LON:BMN), the AIM listed, integrated primary vanadium producer, with ownership of high grade vanadium assets, is pleased to provide a Q2 operational update in respect of Lemur Holdings Limited , the Company’s coal and energy subsidiary that is developing an integrated thermal coal mining and independent power project in Madagascar.

Q2 Highlights:

· A 30-year Project Concession Agreement signed with the Government of Madagascar;

· Inception site visit for Social and Environmental Impact Assessment (“SEIA”) completed;

· Power Purchase Agreement (“PPA”) with state owned utility, Jiro sy Rano Malagasy (“JIRAMA”) amended to allow the utility up to 25MW offtake;

· Draft Bankable Feasibility Study (“BFS”) submitted in June 2018 by technical development partner, Sinohydro and currently being reviewed by the Company; and

· Ongoing engagement with lenders for construction phase of the project. Notably, received Expressions of Interest (“EOIs”) for finance and political risk insurance from two financial institutions.

Details of Operational Update

On 12 May 2018, Lemur, through its Madagascar subsidiary Imaloto Power Project SARL (“IPP”), executed a 30-year concession agreement (“Concession”) with the Government of Madagascar for the Imaloto Power Project. The Concession gives IPP the right to build, own, operate and supply an initial 60 MW in Imaloto, located in the Toliara Province.

In addition, the Concession, gives Lemur the right to build an Evacuation Line of up to 138kV for the transport of the electricity to the connection points.

As one of the primary offtakers, JIRAMA would be able to resell the electricity to residential and large-scale electricity consumers during the specified period, based on the existing PPA which has been increased from 10MW to 25MW.

Furthermore, the Concession enables granting of the right of way and any land use authorisation for the required infrastructure from the coal-fired power plant to the connection points.

The Concession also contains provisions for lenders’ standard terms and conditions to ensure the bankability of the project. In this regard, Lemur continues to engage with potential lenders for the Imaloto Power Project, and has to date received EOIs from two major financial institutions in respect of project finance and political risk insurance. These financial institutions are currently conducting their initial due diligence on the project.

In June 2018, Lemur’s technical development partner, Sinohydro, submitted the BFS for the project which is a critical consideration for the funding phase. The BFS is currently being reviewed by an independent consultant. Once the review is completed and the BFS is finalised, it will provide a more accurate view of project construction costs and associated time lines, which will tie back to the funding discussions with lenders. The BFS will also assist Lemur to progress the Engineering Procurement Construction (“EPC”) discussions. Funding discussions and the negotiation of the EPC contract will be among the key focus areas for the project in the second half of 2018.

In addition to the above, another important milestone achieved during the quarter was the completion of the inception site visit to the Imaloto Power Project area which Lemur and its team of environmental consultants undertook as part of the SEIA. The inception visit was completed in June 2018 and is the first in the series of the SEIA field-based activities that Lemur needs to complete on both the project site and impacted areas. Overall, the SEIA work for Imaloto remains on track and is expected to be completed by Q4 2018.

Prince Nyati, CEO of Lemur Holdings Limited, commented:

“We are pleased that majority of the key elements required to progress the project to the next development phase are in place, in order to supply energy to residential as well as existing and near-term, large power intensive consumers that have not been able to expand or commence operations.

“In addition to progressing the SEIA study and finalising the BFS with Sinohydro, our efforts for the second half of 2018 will focus on advancing project funding and EPC discussions. As part of the SEIA process we continue to engage with the local community. Overall the project will support the regional economy, by creating 1650 direct jobs, some of which have already been filled. However, the majority of jobs will start during the construction phase, which will occur in the next 1 to 2 years.

“Power from the Imaloto Power Project is a viable alternative to existing expensive diesel generation in the region as it will be based on locally produced low-cost exportable coal, combined with clean coal technology that will in turn create demand for abundant unexploited reserves of limestone from the Toliara region. The baseload energy generated by Imaloto is expected to significantly change the economics of mining projects, in the southwest of Madagascar, that were previously deemed as unfeasible.”

Summary of 2018 Project Objectives:

Table 1: Status of 2018 Project Objectives

Objective

Current Status (Q2)

Obtain Project Concession

·   30-year Concession Agreement with government executed

Complete BFS with Sinohydro during H2 CY18

·   Draft BFS completed by Sinohydro

·   Lemur currently reviewing BFS

·   Final BFS dependent upon completion of technical and economic review by independent consultants  

Conclude the SEIA Study by Q4 2018

·   Initial desktop work completed

·   Site inception visit completed

Secure additional offtakes above the current demand from JIRAMA

·   Discussions with private industrial offtakers ongoing

·   PPA with JIRAMA amended to increase up to 25MW

Pursue funding and credit enhancement options for the Project

·   Multiple discussions with various lenders at different stages

·   Received EOIs from 2 major financial institutions– a regional financial institution and a South African government-backed credit insurance agency

·   Both are conducting their due diligence

 

Other Objectives for 2018:

·     Seek to conclude coal offtakes with third parties – coal mine is viable with only supplying coal to the power project. Notwithstanding, supplying coal to third parties provides early cashflows prior to commissioning of the power plant

·     Further explore strategic partnerships for the project (technical, commercial and financial

·     The expected power project commissioning date is 2021

 

Overall, the Imaloto project is on track to deliver electricity to south western Madagascar by 2021.

Click to view all articles for the EPIC:
Or click to view the full company profile:
    Facebook
    Twitter
    LinkedIn
    Bushveld Minerals

    More articles like this

    Bushveld Minerals

    Redox Flow Batteries: technologies and market overview

    This webinar, presented by IDTechEx Technology Analyst Daniele Gatti, will provide an introduction to Redox Flow Batteries (RFBs), addressing some of the technologies developed, and giving an overview of the flow battery market.  The increased adoption

    Bushveld Minerals

    Bushveld eyes delayed JSE debut within 12 months

    Bushveld Minerals, SA’s largest supplier of vanadium, hopes to complete a R1.73bn expansion programme to nearly triple output without calling on its shareholders to fund its plans. Bushveld had delayed its listing on the JSE due

    Bushveld Minerals

    China now a net importer of vanadium

    China is now a net importer of vanadium, a situation which is expected to persist, Bushveld Minerals CEO Fortune Mojapelo said on Tuesday. Speaking at question-and-answer time after presenting a solid set of financial results for 2019, Mojapelo

    Bushveld Minerals

    The coming vanadium battery revolution

    Vanadium: an important role in renewable energy Flow batteries look set to play an important part in the development of the global renewables market, which itself is expected to reach a size of $1.5 trillion by

    Bushveld Minerals

    What is Bespoke Storage

    Bespoke solutions are the largest BESS’s, typically over 20 MW/ 100 MWh, either built into existing buildings, or in purpose built “Storage Stations”. Typical examples of such Storage Stations are the 15MW/ 60MWh system built by

    Bushveld Minerals

    What is a Standalone BESS

    Standalone BESS solutions can be dynamically sized to suit any long-duration storage requirement, typically sized from 100kW/ 400kWh to 40MW/ 160MWh. Standalone solutions are usually made up of multiple containerised units and can stand in any

    Bushveld Minerals

    Hybrid-Mini-Grid

    What is a Hybrid-Mini-Grid A Hybrid-Mini-Grid system comprises of several different sources of energy supply, such as wind or solar, plus diesel back up, plus possibly grid supply, or any other energy resource coupled to a

    Bushveld Minerals

    VRFB Technology

    The VRFB is the simplest and most developed flow battery in mass commercial operations The flow battery was first developed by the National Aeronautics and Space Administration (NASA) in the 1970s and unlike conventional batteries, the

    Bushveld Minerals

    Vanadium flowing in 2020

    2020 was touted by many as the year of the vanadium redox flow battery (VRFB).  In spite of the impact of the global pandemic, this prediction is beginning to bear fruit and the year is only