PowerHouse Energy Group plc Successful Production of Syngas

PowerHouse Energy Group Plc (LON:PHE), the company focused on ultra high temperature gasification waste-to-hydrogen, waste-to-energy, and the creator of Distributed Modular Gasification© (DMG) systems, is pleased to announce that the Company recorded a maximum peak flow rate of over 50 m3 per hour of synthesis gas (“syngas”) having successfully completed the rebuilding and enhancement of the Company’s G3-UHt gasification reactor at the Thornton Science Park. This is the second successful phase in the operation of the G3-UHt unit in the UK and the first at the Thornton Science Park.

Since the re-siting of the unit at Thornton in early May, the technical team have been working on integrating the G3-UHt system into the Energy Centre facility at Thornton, as well as aligning the system and the utilities to take best advantage of the research facilities available. Through this period a number of improvements and modifications to the G3-UHt system have been made, ahead of the scaling up necessary for commercial deployment. These have included the enhancement of the gas systems, refurbishment of the feed and steam generation systems, the complete redesign and introduction of programmable safety and control systems designed in line with UK Health, Safety, & Environment (“HSE”) legislation.

This latest commissioning, the positive engagement of senior planning and permitting personnel from the local Council, and the completion of a rigorous third party review to allow insurance cover to be put in place now positions the G3-UHt to begin full-scale, and on-going, operation, testing, and demonstration at the Thornton site.

Following an extensive pre-commissioning programme, the 24 hour commission testing this weekend used tyre crumb as the input feedstock and produced a robust stream of syngas which was safely flared to the atmosphere. Subsequent testing will allow for a thorough analysis of the syngas produced, however, in-line, real-time analysis indicated that the quality of the gas produced met the Company’s initial quality objectives and there was full combustion of the syngas at the flare. The system was taken through cool-down and the team undertook post-operational review .

The demonstration unit at Thornton is critical to the next stage of modelling and process design. The conceptual design for the commercial modules will continue to be augmented by the operational input from the G3-UHt demonstrator. It is expected that the next few months should bring a number of industry players to Thornton, as well as potential commercial partners and interested shareholders. It is intended that the Company will host one or more demonstration visits for investors at the Thornton Science Park in September and full details will be announced in due course.

Pursuant to the announcement of 5 June 2017 the successful re-commissioning and operation of the G3-UHt at Thornton has released the first £100,000 tranche of a potential £500,000 from a UK partner dedicated to the planning and permitting of the Company’s first commercial sites.

David Ryan, Powerhouse Executive Director of Programme Development said: “The PowerHouse team were superbly supported by our design consultants Engsolve, the service company, Roseberry and IDM. All have worked extremely hard and to a tight timescale to achieve this milestone. We were aided and supported at each stage by the staff of the University of Chester and by the support staff at the Thornton Energy Centre. The sight and sound of gas production at the flare was a great manifestation of all the hard work.

“This extended operation at high temperature was an excellent result and we look forward to the planned commercialisation programme with enthusiasm.”

Commenting, Keith Allaun, Executive Chairman of PowerHouse Energy Group Plc, said: “This is a hugely important milestone for the Company and one that our long-standing shareholders have been waiting for. With the successful initiation of our programme at Thornton, we can now begin to aggressively pursue our commercial agenda. The ability to regularly operate, demonstrate, and test the G3-UHt at Thornton allows us to begin the 25 tonne per day design engineering. The active engagement of the University of Chester faculty, the Ph.D program we’re co-sponsoring in ultra-high temperature gasification, coupled with our talented engineering team and programme leadership ensures that PowerHouse will lead the market in the deployment of distributed waste-to-hydrogen and waste-to-energy solutions. Distributed Modular Gasification© has only begun to make its mark and disrupt the industry. The opportunities ahead of us appear unlimited.”

Click to view all articles for the EPIC:
Or click to view the full company profile:
    Facebook
    Twitter
    LinkedIn
    Powerhouse Energy Group Plc

    More articles like this

    What is DMG?

    Distributed Modular System (DMG) technology can: convert unrecyclable plastic into high-grade hydrogenfor use as a transport fuel generate power for exportby private wire or to the grid Powerhouse Energy Group PLC (LON:PHE) has developed the innovative

    The future of waste-to-energy technology

    We produce over 2 billion tons of waste per year, a number that’s expected to grow by 70% by 2050. We’ve long sought ways to turn all this waste into energy, but this has usually meant

    Progress made on plastic to hydrogen sites

    The development of hydrogen production from waste plastics sites across the UK is set to accelerate following a supplemental collaboration agreement between PowerHouse Energy Group and Peel Environmental signed yesterday. The collaboration will focus on the

    Waste to Energy

    Waste to Energy (WTE), is a term that is used to describe various technologies that convert non-recyclable waste into usable forms of energy including heat, fuels and electricity. WTE can occur through a number of processes such

    Waste to energy capacity continues to grow in Europe

    Waste to energy is still a growth market in Europe. The number of facilities commissioned is set to rise in the years ahead, the consulting firm Ecoprog announced at the publication of the latest edition of

    Meet Waste2Tricity

    Whether buying sliced ham in a black plastic tray or high-value gadgets cosseted in polystyrene, taking an environmentally-friendly route when disposing of the vast array of packaging we’re bombarded with can often seem akin to navigating a minefield.